Liaoning Huaneng Dandong Power Plant Project
(1996-1998)

      Liaoning Huaneng Dandong Power Plant imported 2x350MW power generating units from USA,  and NEPC undertook all civil works of both units and erection work of Unit l. The project was honored with The Year 2001 China Construction Engineering Luban Prize (National Quality Project) .

 

Henan Huaneng Qinbei Power Plant Phase I (2x600MW Supercritical Units) Erection Project
(2003-2004)

       Henan Huaneng Qinbei Power Plant Phase I (2 x 600MW supercritical units) project is a large thermal power plant project newly proposed during the "10th five-year plan" in China. It is a self-reliance supporting project of the 600MW supercritical unit made in China, and also a pilot project for the demonstration design of the coal-fired power plant in the 21st century. NEPC undertook the erection works of Unit l. The project won the Year 2006 China Construction  Engineering Luban Prize and China Electric Power High Quality Project Award.

 
Shenhua Guohua Huanghua Power Plant Phase I (2 x600MW units) Unit 2 Civil & Erection Project
(2004-2006)

       As one of key engineering projects in China, Hebei Shenhua Guohua Huanghua Power Plant Phase I (2 x600MW units) Project is integrated with the biggest 600MW steam extraction generating unit in China, enclosing and filling sea water to make land, combination harbor and power plant and sea water desalting. NEPC undertook the erection work of Unit 2 and was honored with the Year 2008 China Construction Engi-neering Luban Prize and the China Electric Power High Quality Project Award.

Anhui Huaneng Chaohu Power Newly Built (2x600MW Supercritical Units) Project
(2007-2008)

       The project was the first optimized 600MW supercritical coal fired unit in China. NEPC undertook the erection work of Unit l. The Project was honored with "The Year 2009 China Electric Power High Quality Project Award", "The Year 2009 Electric Power Industry up to Standard Project Award" and " The Year 2010 Silver Award of China High Quality Project"

 

Liaoning Shenhua-Guohua-Suizhong Power Plant Phase II (2 xl000MW units) Expansion Project Unit 4, Civil & Erection Project
(2007-2010)

       This project is the first 1000MW generating unit in Northeast China. NEPC undertook the civil and erection of Unit 4, coal handling system and circulating water system of Phase II expansion project. During the construction, NEPC scrupulously and respectfully abides by the principle of being honest and keeping faith, attaches importance to the credit of our brand, and NEPC has assured the accomplishment of the various construction tasks as scheduled with safety, high quality, and won the praise from clients with the stronger contract fulfilling capability ensuring that interior quality and exterior workmanship reach the leading level of the same kind under construction at the same period in China. The Project was honored with The Year 2011 China High Qual-ity Project Gold Prize and The Year 2011 National High Quality Project Award.

 Jilin Huaneng Jiutai Power Plant (2x 600MW Supercritical Units) Project (2008-2009)

       The unit is equipped with tower-type boiler, with steel frame at the weight of 19500 tons. The boiler is 135.25 meters high and 33000 tons weight, and 63596 welded joints. NEPC undertook the erection work of unit 2. This Project won The Year 2011 National Quality Project Silver Medal and The Year 2011 National Electric Power Quality Project Prize. 